'Shovel ready': National Grid helps 20GW of clean energy projects jump connections queue

National Grid is fast-tracking the connection of 20GW of clean energy projects across England and Wales through two main initiatives:

  1. Transmission Network (10GW):
  • 19 battery storage projects will be connected approximately four years earlier than originally planned
  • This is achieved by allowing batteries to connect before completing non-essential engineering works
  • Battery operation will be managed by the ESO to reduce system impact
  • Additional 10GW of mainly battery and hybrid projects may be accelerated in a future phase
  1. Distribution Network (10GW):
  • Focuses on the Midlands, South West England, and South Wales
  • Over 200 projects have shown interest in fast-tracked connections
  • 16 projects could connect within 12 months
  • 180 projects aim to connect within 2-5 years
  • Some 'shovel ready' projects could be advanced by up to 5 years

The total 20GW capacity equals six Hinkley Point C nuclear power stations. This initiative is part of a broader collaboration between transmission and distribution networks, working with industry, Ofgem, and the government to accelerate clean energy connections.

Read the Article

Further Reading

Hitachi

Smart Islands Energy Project

Empowering the Isles of Scilly community to better utilise renewable energy within the network

More

AndAnotherDay

Innovative digital products for organisations and businesses who align with the UN SDGs

Get in touch with us today to discuss your project and how we can help.

Contact us